Timeline for Building Construction
 

Much progress is being made in our efforts at Dallas Lutheran School to Arise & Build.  Our master campus plan will provide new educational and administrative facilities to support students in our community for the next generation.

Currently, the school’s Board of Trustees Building Committee and other leaders are working with architectural firms, building contractors, and city officials to prepare for new construction to begin late spring / early summer of 2022, with a targeted Phase 1 completion date anticipated for Fall 2023.

Phase 1 of the construction will accommodate up to 200 students.  Additional phases of the construction will be needed for additional classroom space, athletic fields, and a new chapel / performance center.

TIMELINE DETAILS

Planning and Zoning:

  • Application submitted: 1/12/22
  • Anticipated City Council Approval: May 2022*

Engineering (underground utilities and connections, paving, grading, etc.):

  • Plans Submitted: by 1/31/22
  • Estimated City Approval: mid-July 2022*

Buildings and Site (Architectural, Structural, MEP and Landscape):

  • Schematic Design and Pricing: January 2022
  • Design Development and Pricing: March 2022
  • Construction Documents / Issue for Building Permit and Pricing: May 2022
  • Final Construction Documents for Bidding & Construction: June 2022
  • Estimated Permit Approval: mid-July 2022

Demolition:

  • Relocate Servers: March 2022
  • Demolish Remainder of Art/Science Wing: June 2022

Construction:

  • 3-way (city engineering) contracts prepared and executed: July 2022*
  • Final Pricing: July 2022
  • Construction Agreement executed: July 2022
  • Notice to Proceed (site mobilization): July 2022*
  • Construction: approximately 12 months
  • Substantial Completion: 8/1/23
Dates are based on current timetable and are subject to change.
 

*item(s) contingent on engineering, zoning, and/or building permit approvals